Show relationship between group of activities

 

 

Sometimes we want to simplify our Gant chart report.

 

In stead of a report like this with so many relationships connecting between all activities:

1

We can make it more simple by showing only summary level and relationship between them:

It’s very useful for Manager level when they only need to see the summary level.

I will show you how to do this.

Go to Layout -> Bar Chart Option:

Go to Collapsed Bars tab -> Check “Show relationships for collapsed bars”

4

Now when you collapse activities to a summary level, there will be a relationship connecting them.