Blogs


Where the Engineering work sequence does not match that of construction….

 

For that reason, Civil Works Installation drawings (page 88), complete with all underground objects and networks, are required very early, for construction reasons, as completion of civil works is a pre-requisite for mechanical works to proceed.

The irony is that these drawings come last in the Engineering work sequence. Take the example of the drains. This is the last network Process engineer will care about… It will nevertheless be a show stopper for the installation of process lines, which will have been designed much earlier.

Related Posts

Categories

Search