Turn off Auto Compute Actual for activities in Primavera P6


By default our project check this option like below image so that when you update Duration % complete, P6 will update Actual units for you.

1

When you don’t want this happen, you can turn it off. However it will apply to the whole project.

How about you want to turn it off for only one activity.

There is another way to turn it off by go to the Resource dictionary and turn off for that resource.

However it will apply to all resource assignment in your project.

It’s impossible. You want to turn off for only 1 activity.

And I find out there is 1 solution.

The option “Recalculate Actual Units and Cost when duration % complete changes” doesn’t affect activity which is “Fix Units” or “Fix Units/time”.

So you can change the Duration type of that activity to “Fix Units” or “Fix Units/time”.

Now when you update Duration % complete, it doesn’t automatically update actual units.

Tags:
Continue reading
21054 Hits
0 comments

Can not filter on Start or Finish date

Can not filter on Start or Finish date

 You have a very simple project. You want to show only activity which finish on 25-Jan-16.

1

As usual, you create an filter like this:

2

Then… SURPRISE. It’s a blank screen.

A big “WHY” question.

To answer this question. You need to show the time of activity by going to Edit -> User Preferences -> Dates tab -> In “Time” section, click on “24 hour”

4

Now you can see the Time when activity start and finish.

You can notice that when we define the filter, by default the Time is 00:00. That’s why P6 can not find any activity.

6

So we can change the criteria to cover the whole day like this:

7Now P6 can show the activity which has finish date of 25-Jan-16.

 

 

Tags:
Continue reading
20222 Hits
0 comments

EV (Earned Value) Maturity - Its benefits and why it is important

Often there is discussion on why the EV needs to be matured and what are its benefits - tangible and as well as non tangible. I am making a small attempt to list some its benefits and keen to know your thoughts - 

The benefits of improved EVM at enterprise or PMO level:

- Standardised processes for managing project performance on a programme
- Improves transparency and strategic reporting senior management through
dashboards
- Improved timeliness and quality of reports through streamlined reporting
- Improved standardisation and automation of reports resulting in reduced
costs for report production and improved employee job satisfaction for
project controls teams members
- Employee development of competencies
- Produces historical data that can be used for lessons learned and to
improve future estimating
- Produces man-hour utilisation and productivity statistics for HR
planning
- Improved compliance with corporate financial reporting requirements
- Provides valuable strategic and operational information for improved
decision making (high tangibility)
- Reduced costs and increased benefits through improved project and
program decision making (low tangibility)
- Reduced reporting cycle times
- Improved communication and standardised processes for project
estimating, planning, scheduling, cost control, contracts administration
and project accountants.

The benefits of improved EVM maturity at project level:

- Continuous feedback on project work progress and productivity
- Early identification of performance trends and root causes
- Improves transparency and reduces the risk of disputes between owner and
contractor
- Improves project forecasting, planning of key resources
- Produces historical data that can be used for lessons learned and to
improve future estimating
- Produces quantity statistics, man-hour statistics and other data that
can be used by other functions such as safety

Thanks for reading. 

Anil Godhawale
Managing Director, Projcon Group

Continue reading
4478 Hits
0 comments

Print report to show predecessors in Gantt chart

 

To show Predecessors of an activity we can use Relationship tab:

 

1

However it’s quite difficult to identify what are those activity.

How about we can show them in Gantt chart. That will be more easy to understand.

First you choose View -> Collapse All.

Go to the activity you want to show Predecessors. Select a Predecessors and click the GoTo button.

When you click it, you will jump to that Predecessor, and the WBS of that predecessor will expand.

You will do one by one predecessor.

To hide all other unnecessary bar, you can read this article : https://doduykhuong.wordpress.com/2016/02/19/make-report-to-show-only-some-wbs-in-gantt-chart/

Now you will have a report which show all predecessors in Gantt chart:

Tags:
Continue reading
4502 Hits
0 comments

Critical path by Total Float is wrong in multiple calendar project

 

We have 4 activities which have same calendar : Standard 5 day workweek. We use Total Float to calculate Critical path. The result is this:

When I change A1020 activity’s calendar to 1 Day Workweek. We use Total Float to calculate Critical path. The result is this:

You can see it’s wrong critical path.

Now when you choose Longest path option. It will become like this:

3

Now the critical path is better:-)

So when you have multiple calendar project, consider to use Longest path option.

 

Tags:
Continue reading
4565 Hits
0 comments

When do we use "Store Period Performance" function?

When do we use “Store Period Performance” function?

2
 

In my project, I receive updated data from construction team every month. However, they never update data correctly in that period.

For example, this month is December, most of activity they update start and finish within December but there are always some activities which is updated in November or even in October. (They said they forget to update those activities in November so now they update it this month).

In this case P6 will add some more units to November and make your November report wrong. You have sent November report to other parties and it can not be edited. So, the only solution is you move all November “mistake” unit to December.


 

 

You can use Excel to save figure of November and December. Then we can have Actual this month by taking December minus November.

However, we can do this right in Primavera.

First in November you need to run Tool -> Store period performance, to storage Actual Units (in fact this is the cumulative actual unit) to November period.

In December you just update as normal. Now you can show the “Actual This Period Units” column. And that’s the data we need.

 